A plow route is not a mowing route with a blade on the front. The constraints are different: some properties have hard deadlines before businesses open, some need a skid steer or a loader instead of a pickup, and the snow has to go somewhere that does not block drains or sightlines. Get the route wrong and your best operator spends the night driving past lots he should have cleared. This post covers how to group snow properties into routes, match equipment to the work, and keep routes realistic through a long winter.
Start with deadlines, then geography
In summer, you group properties by area and pick an order that minimizes driving. In winter, deadlines come first. A retail lot that must be clear by 6am and a medical office that opens at 7 cannot wait for a truck to finish twelve driveways first.
Build routes in two layers. First, list properties with hard deadlines and group them by area into the first part of each truck's route. Then fill in properties with flexible timing after them, in the same general area. A truck that clears three commercial lots in one neighborhood by 5am and then does the driveways nearby is far more effective than one zigzagging between deadlines.
Commercial deadlines are not all the same, either. A grocery store may open at 6am but receive deliveries at 4am, which means the loading dock has to be clear before the lot. A church may need its lot on Sunday morning but not on Saturday night. A medical office may need its entrance and handicapped spaces done first. Put the real deadline and any special order on each property so the operator sees it, not just the office.
Match the equipment to the property
Different properties need different equipment. A residential driveway is a pickup with a straight blade or a snowblower. A big retail lot may need a truck with a wing plow or a loader with a pusher box. Sidewalks need a walk crew with shovels, blowers or a small machine. Plan routes by equipment type, not just by area.
Note on each property which equipment it needs and roughly how long it takes with that equipment. A lot that takes a pickup 90 minutes may take a loader with a pusher 25. That difference changes which truck the property belongs to. Keep walk crews on their own routes that follow the plow trucks, so sidewalks and entrances are done after the lot, not before it gets plowed back over.
Plan where the snow goes
Every property needs a plan for piling snow, and it belongs in the property notes before winter. Good spots are away from storm drains, not in front of fire hydrants, not blocking sightlines at exits, not on landscaped beds you will be repairing in spring, and downhill of walkways so meltwater does not run across them and refreeze.
Mark the spots on a photo or a simple sketch and add it to the property. A new operator who has never seen the lot will know where to push. After a few large storms, piles can block parking or create melt problems. Plan for relocation or hauling, and price it in the contract as an extra.
Order each truck by distance
Once properties are grouped by deadline and equipment, order each truck's stops to minimize driving within each priority group. Auto-routing orders a day's stops by distance, and you can adjust the result for the few things it does not know, like a one-way street or a lot that is easier to enter from the back.
Watch for one common mistake: a route that is efficient on paper but forces a plow truck to make a long run on a highway between two clusters. Snow-covered roads are slower than summer roads, sometimes much slower. Keep each truck's properties as close together as you can, even if that means more trucks with shorter routes. See route optimization for how stop order is calculated.
Balance trucks by hours, not by count
Ten properties is not a unit of work. Ten driveways might take three hours. Ten commercial lots might take twelve. Balance routes by estimated hours, using the push time noted on each property, plus realistic drive time in snow.
After the first few storms, compare estimates with reality. Clock-in and clock-out times and completion times per stop tell you how long each property really took. Adjust the estimates and rebalance routes before the next storm. A route that runs four hours over its plan on every storm is not a crew problem, it is a planning problem. The GPS and clock times post covers how to use those records.
Plan for breakdowns and absent operators
Something will go wrong on a big storm. A truck will break a hydraulic line, an operator will get sick, or a contract property will need three passes instead of one. Have a plan before it happens. Know which truck can absorb another route's priority properties, keep a spare operator on call when you can, and know which properties can wait a few hours without a problem.
When a truck goes down, move its unfinished properties to other trucks in the schedule. The operators see the new stops on their phones. Tell affected customers if their service will be later than usual. A short message about a delay is far better than silence and a missed opening time. The storm call post covers deciding when to send crews out.
Drive the routes before the first snow
Before the first storm, have each operator drive his route in daylight. Look at every property with fresh eyes: where the curbs are, where the islands start, which speed bumps will catch a blade, where the drains sit, what is buried under the first snow. Mark curb lines with stakes or reflectors where the contract allows. Update the property notes with anything new.
A dry run also tests the route order. An operator who drives it once will spot the left turn that takes five minutes, the property that is easier to enter from the back alley, or the two properties that should swap trucks. Fix those in October, not at 3am in January. Time the dry run too. It will not tell you plowing time, but it will show you the drive time between stops on clear roads, and you can add a margin for snow.