Did That Storm Make Money? Job Costing for Snow Removal

October 21, 20264 min read

After a big storm, most snow contractors know roughly what they billed. Few know what each property cost them. That matters because snow prices are set once, before winter, and then the weather decides how much work each property needs. A lot that looked fine on paper may take twice as long as estimated every storm, or eat salt at three times the expected rate. Without job costing, you find out at the end of the season when the bank account looks thinner than the invoices suggested. This post covers how to cost snow jobs and what to do with the numbers.

The three costs that matter

Snow job costs come from three places. Labor, which is operator and walk crew hours times pay rate. Materials, mostly salt and ice melt, priced from what you paid. And equipment, the cost of running trucks, plows, loaders and spreaders, including fuel, wear and the share of payments and insurance.

Labor and materials can be tracked per property. Job costing pulls labor from crew clock-in times times each worker's pay rate, adds the materials used, and shows profit and margin per job. Equipment is harder to tie to a single property, so many contractors use an hourly equipment rate per truck or machine and add it to labor time.

Labor from clock times

Labor is usually the largest cost in snow work. Clock-in and clock-out times give you each operator's hours on each storm. Pay rates are set per worker and kept office-only, so operators do not see each other's pay. The job costing report puts the two together.

The tricky part is time between properties. A route with ten properties and eight hours of clock time had some drive time in it. Decide how you want to handle it: spread it across the properties on the route, or report it separately as a route cost. Either is fine as long as you are consistent. What matters is that the total labor cost of the storm is accounted for somewhere.

Overtime changes the math. Storm shifts often push operators past 40 hours in a week, and overtime hours cost more. When you look at labor cost per property, use the actual pay for those hours, including overtime, not just the base rate. A property serviced late in a long storm week may cost noticeably more in labor than the same property serviced early in a quiet one. That is not a reason to skip it, but it is a reason to price your heavy-winter tiers with some room for overtime built in.

Salt and materials

Salt and ice melt usage comes from the application records operators log at each property. Multiply by your cost per unit from the materials list. Keep the material costs current, because salt prices can change between seasons or even mid-season.

Watch for properties where salt cost is far above your estimate. A shaded entrance, a sloped lot or a property manager who calls for extra treatments can push salt cost well past what your price assumed. Our salt records post covers what to record and how to keep operators consistent.

Putting a cost on equipment

Equipment cost is the one most contractors skip, and it is often large. A truck with a plow and spreader has a payment or depreciation, insurance, fuel, maintenance, blade edges and repairs. A loader or skid steer has the same, plus transport.

A simple way to handle it is an hourly equipment rate. Add up a machine's yearly costs, divide by the hours you expect it to work in a season, and use that rate per hour of use. Say a plow truck costs $12,000 a year all in and works 300 hours in a typical winter. That is about $40 an hour. Add it to labor time for each property the truck serviced. The number will not be exact, because a heavy winter means more hours and a lower rate per hour, but it is far better than leaving equipment out. Without it, every property looks more profitable than it really is.

Planned versus actual hours

Every property should have a planned time per push, from your estimate. After each storm, compare it with actual time. Most properties will be close. A few will be far over. Those are where your money is going.

Look for the cause. Cars left in the lot that the operator had to plow around. A new obstacle like a dumpster or a construction fence. An operator unfamiliar with the property. Snow piles that have grown so large the operator spends extra time stacking. Some causes can be fixed with the customer, like a request to clear cars by a certain time. Others mean the price needs to change at renewal.

Comparing billing models by property

Job costing shows how each billing model performed. Per-push properties should show steady margin per push, because pay tracks work. Seasonal properties will vary: very profitable in a light winter, possibly losing money in a heavy one.

At the end of each winter, look at margin by property and by model. A seasonal property that lost money in an average winter needs a higher price, a cap or a switch to per push. A per-push property with thin margin needs a rate increase or a closer look at how long it really takes. The billing models post covers how to set up each model.

Use the numbers at renewal

Snow contracts are usually renewed once a year, so the end of winter is when job costing pays off. Run the job costing report by property for the season. Sort by margin. Look at the bottom ten properties and decide for each: raise the price, change the model, change the scope, or let it go.

Bring numbers to the conversation. "Your lot took an average of 95 minutes per push this winter, against 50 estimated, mostly because of cars left overnight. We need to either adjust the price or agree on a clear-by time." Most property managers respond better to that than to a flat increase. The reporting tools cover the job costing report and other season reports.